Monday, August 30, and Tuesday, August 31,
Nightly from 9pm to 5am
- Southbound I-110 which connects US 54 to the Bridge of the Americas will be closed to all traffic.
- DETOUR: Traffic bound for Juárez should use another port of entry.
Crews will be installing light poles and overhead signs.
|
|
Wednesday, September 1, from 9pm to 5am
- Westbound I-10 will be closed to all traffic between Trowbridge Drive and Raynolds Street
- I-10 DETOUR: Take Exit 24 (Geronimo Drive/Trowbridge Drive), continue on Gateway Boulevard West, re-enter I-10 at Raynolds Street.
- US 54/JUÁREZ DETOUR: Use the above detour, turn right on Chelsea Street, turn left on Montana Avenue, enter US 54 at Montana
Crews will be relocating concrete safety barriers.
|
|
Thursday, September 2, from 9pm to 5am
- Eastbound I-10 will be reduced to a single lane from US 54 to Trowbridge Drive.
- Ramp D, which connects southbound US 54 to eastbound I-10, will be reduced to a single lane.
Crews will be relocating concrete safety barriers.
|
|
Ongoing closures which will continue without interruption
- Ramp F which connects westbound I-10 to southbound US 54 and Juárez remains closed until further notice.
- US 62 (Paisano Drive) remains closed to traffic in both directions between San Marcial Street and Gateway Boulevard South.
- Gateway Boulevard East remains closed to thru traffic between Loop 478 (Copia Street) and Marr Street.
- The ramp from southbound US 54 to US 62 (Paisano Drive) remains closed until further notice.
- Both turnarounds under US 54 at US 62 (Paisano Drive) remains closed until further notice.
- Intermittent closures on Durazno Avenue, Rosa Avenue and Uva Street.
- Intermittent lane closures on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
- Intermittent lane closures on Gateway Boulevard West between Boone Street and Palm Street.
THESE CLOSURES ARE SUBJECT TO CHANGE DUE TO WEATHER.
|
|
About the I-10 Connect Project
The I-10 Connect project is at the intersection of Interstate 10 and US 54 in El Paso County. The project extends from I-10 to Loop 375 (Cesar Chávez Border Highway) and provides access to the Bridge of the Americas (BOTA) via I-110. The $96 million project includes the construction of four new direct connectors, a full reconstruction of the I-110/US 62 (Paisano Drive) interchange, and removes exit ramps from US 62 to I-110.
I-10 Connect will improve connectivity between I-10 and Loop 375, also providing an alternate route to I-10. It started February 19, 2019, and is expected to be complete in less than three years.
|
|
|
|