December 3, 2018 - This is a reminder that there will be a series of road closures next week as the project intensifies. 
  • 11 p.m., Tuesday, December 11, 2018 to 5:30 a.m., Wednesday, December 12, 2018: There is the planned closure of Kūhiō Highway (Route 560) at the Wai‘oli Stream Bridge between Anae Road and Kumu Road in Hanalei.
  • Monday, Dec. 10 to Friday, Dec. 14, 8:30 a.m. to 2:30 p.m.: A single lane of Kuhio Highway (Route 560) will be closed daily for survey work between Hanalei Bridge and Hanalei Plantation Road. The survey work will support the design of slope stabilization project on the hillside adjacent to Kuhio Highway.  During work hours flagmen will alternate traffic operations through the open lane. Motorists should expect delays and travel with caution through the work zone.
All work is weather permitting. Should conditions necessitate changes in the roadwork schedule, the latest information will be posted on the HDOT roadwork page at http://hidot.hawaii.gov/highways/roadwork/hawaii/ or via the Department’s Facebook and Twitter accounts.
 
Earlier this week, per request of the community, the culvert at the Lumaha‘i Ford was cleared out to reduce debris and improve water flow.  
 
Visit the Hawai‘i Department of Transportation Project Website
The project continues to make progress along Kūhiō Highway. Below youʻll find a full project status update of the various work sites along Route 560 (Kūhiō Highway). Project activity will continue to intensify in upcoming weeks. 
Project Status (as of 12/07/2018) – View the table below for a list of HDOT repair projects and current progress. 
 
# Location Description of work Progress
Hā‘ena to Hanalei
1 Route 560, MP 10 at Kē‘ē State Park Reconstruct roadway. Texture, finish, and staining complete. Revetment, CRM, paving, and guardrail to be scheduled. 
2 Route 560, MP 9.55 at Limahuli Stream Crossing Repair concrete section lost in flooding. Resurface ford crossing. Design in progress. Debris cleared from culvert. 
3 Route 560, MP 8.7 at Hā‘ena Beach Park Repair roadway shoulder. No staining required, wall complete. Schedule for paving and guardrail to be scheduled.
4 Route 560, MP 8.76 at Mānoa Stream Ford Crossing near Hā‘ena Beach Park Repair entire crossing. Design in progress.
5 Route 560, MP 6.5 Repair Site 2  Debris removal, slope wall installation including soil nails, foot of slope
revetment, guardrail/sign replacement, pavement repair.
Soil nail, shotcrete, texture and finish work has been completed.  Revetment in progress. CRM wall, paving and guardrail to be scheduled.
6 Route 560, 15 or more locations between MP 6.5 and 4.4 (Land slide zones) Debris removal, slope scaling, slope stabilization, guardrail replacements, pavement repairs. The majority of debris removal and slope scaling complete.  Currently stabilizing the slope in two most critical slopes (Slides A & B).
7 Slides A & B Slope scaling and reinforcement.
Started excavation, soil nail anchor and wire mesh installation at slide B in progress. Drainage swale to be scheduled.
 
8 Route 560, MP 6.3 Repair Site 3 Roadway stabilization area. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair. Soil nail, reinforcement, and shotcrete placement has been completed.  Staining, paving, and guardrail to be scheduled.
9 Route 560, MP 6.2 Repair Site 4 Roadway stabilization area. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair.

Soil nail work has been completed. Reinforcing and shotcrete layer work, texture and staining are complete. Paving and guardrail work to be scheduled.
 
10 Route 560, Repair Site 5 Slope reinforcement. Soil nail work scheduled to start after the completion of sites 3, 4 and slides A & B.
 
11 Route 560, Repair Site 6 Slope reinforcement Soil nail, shotcrete, texture and staining and completed.  Revetment Wall, CRM Wall, paving and guardrail to be scheduled.
 
12 Route 560, MP 5.8 Lumaha‘i Stockpile area Stockpiles are being maintained and erosion control measures are being implemented.
13 Route 560, MP 4.5 Repair Site 1  Roadway stabilization area. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair. Soil nail and shotcrete work has been completed.  Texture and finish work is ongoing.  Paving and guardrail to be scheduled.
14 Route 560, MP 4.4 Waikoko Stockpile area
Stockpiles are being maintained and erosion control measures are being implemented.
 
15 Waikoko Bridge Replace existing bridge
Clearing vegetation for utility relocation & laydown areas, utility relocation, constructing equipment pads.
 
16 Waipā Bridge Replace existing bridge Clearing vegetation for utility relocation, constructing equipment work pads. 
17 Route 560, MP 3.7 Staging area Staging area currently in use.
18 Wai‘oli Bridge Rehabilitate existing bridge, remove
debris from under bridge

Removing unsound concrete at existing bridge railings and replacing with new concrete. Removing existing asphalt concrete (AC) pavement scheduled for Dec. 11. 
 
19 Route 560, MP 1 Debris removal, slope scaling, guardrail replacements, minor pavement repair (April). Slope stabilization (Lane). Repairs from April Flood had been completed. Currently preparing scope of work from Lane damages.
20 Route 560, MP 0.5, near Hanalei Bridge Debris removal and slope clean-up. Complete.
Kalihiwai
21 Route 56, MP 25 Debris removal, slope scaling. Complete.
22 Route 56, MP 24.9 Debris removal from under bridge, CRM
wall replacement
Debris removal complete. CRM wall in design.
Wailua
23 Wailua Bridge Debris removal from river under bridge (April). Adding scour protection post Lane. Debris removal complete.  Scour protection measures in design.
         
 

Questions? Comments?

You can reach our project team via email by clicking here or by calling our 24 hour hotline at (808) 230-0796 or toll-free at 1 (800) 722-9012.

We are still continuing to build our newsletter distribution list. You can assist in that effort by forwarding this email as appropriate. To sign up for updates, click here

Kaua‘i County Website on the April 2018 Flooding

The Kaua‘i Emergency Management Agency has established a website with information on how to get a resident placard, work pass, or shuttle pass for access to Wainiha and Hā‘ena.

Go to Kaua‘i County Website

Convoy Schedule

A request for a 6:00 a.m. addition to the Sunday / Holiday convoy schedule was received by the Department to allow residents with early morning shifts to get to work on time. That request was approved by the Department. A link of the revised convoy schedule, which began November 22, is available here.

Note: this does not include the schedule for the shuttle operated by the Hanalei Colony Resort.

A request for a mid-morning 10:30 a.m. convoy was received by the Department. Unfortunately, with the accelerated project schedule, we are unable to accommodate this request at this time. We sincerely apologize for this inconvenience. 

Repair Schedule

The initial target for completion of work and reopening of Kuhio Highway between Waikoko and Wainiha was late 2018. After accounting for weather-related delays and consideration of environmental and community concerns, the Department announced in early November that HDOT is now targeting early 2019 for reopening of the road.

A chart showing remaining work needed to reopen the road without convoys and completion targets is available at this link.

Road closures, including weekend closures with ferry access, may be scheduled after the early 2019 timeframe. The estimated completion date for the bridge work on the 3 Ws is Spring 2019. Advance notice of road closures will go out via HDOT’s lane closure notices and the Kuhio Highway Emergency Repairs mailing list.

By community request, we have added the link to the Department of Land and Natural Resources Division of State Parks page for the Hā‘ena State Park. You can visit this site for updates on repairs and upgrades to the park.

Enjoy Previous Editions of Our Newsletter!

Newsletter #1 (Released October 19, 2018) 
http://bit.ly/KuhioHighwayOct19
Newsletter #2 (Released October 26, 2018)
http://bit.ly/KuhioHighwayOct26
Newsletter #3 (Released November 2, 2018)
http://bit.ly/KuhioHighwayNov2
Newsletter #4 (Released November 9, 2018)
http://bit.ly/KuhioHighwayNov9
Newsletter #5 (Released November 16, 2018)
http://bit.ly/KuhioHighwayNov16
Newsletter #6 (Released November 23, 2018)
http://bit.ly/KuhioHighwayNov23 
Newsletter #7 (Released November 30, 2018)
http://bit.ly/KuhioHighwayNov30

Read Previous Project-Related State of Hawai‘i Department of Transportation News Releases


HDOT assesses flood damaged areas on Kauai; outlines steps needed to reopen Kuhio Highway (April 17, 2018)
Status of recovery for Kuhio Highway from Waikoko to Wainiha following April 14 flooding (April 20, 2018)
Update on restoration of Kuhio Highway from Waikoko to Wainiha following April 14 flooding (April 26, 2018)
Kuhio Highway from Waikoko to Wainiha to open to local traffic only beginning Friday, May 4 (May 3, 2018)
May 5 update on local access to Kuhio Highway from Waikoko to Wainiha (May 5, 2018)
Memorial Day schedule for local access to Kuhio Highway between Waikoko and Wainiha (May 27, 2018)
Schedule for local access to Kuhio Highway between Waikoko and Wainiha updated (May 29, 2018)
Update to schedule for local late-night convoy for Kuhio Highway between Waikoko and Wainiha (May 30, 2018)
Weight restriction on Kuhio Highway on Kauai’s north shore increased to 8 tons (June 1, 2018)
Timeline on Kuhio Highway emergency flood repairs (June 8, 2018)
June 19, 2018 Kuhio Highway emergency flood repair update (June 19, 2018)
Updated schedule for limited local access to Wainiha, Haena via Kuhio Highway (June 21, 2018)
Single lane closure on Kuhio Highway in Princeville and Hanalei for road maintenance (July 19, 2018)
Single lane closure will continue next week on Kuhio Highway in Princeville and Hanalei for roadside maintenance (July 26, 2018)
Updated schedule for limited local access to Wainiha, Haena via Kuhio Highway begins August 6 (August 1, 2018)
Changes to the updated schedule for limited local access to Wainiha, Haena via Kuhio Highway beginning August 6 (August 3, 2018)
Updated schedule for limited local access to Wainiha, Haena via Kuhio Highway effective October 15 (August 13, 2018)
HDOT is preparing for Hurricane Lane (August 21, 2018)
Schedule for limited access to the north shore of Kauai for Hurricane Lane (August 21, 2018)
HDOT Highways update on Hurricane Lane, August 22, 2018 (August 22, 2018)
HDOT update on Hurricane Lane, August 23, 2018 (August 23, 2018)
HDOT 5 PM update on Tropical Storm Lane (August 24, 2018)
HDOT update on Tropical Storm Lane, August 25, 2018 (August 25, 2018)
Effects of remnants of Tropical Cyclone Lane on State Routes (August 28, 2018)
Kuhio Highway Emergency Repairs to be reevaluated following flooding from remnants of Tropical Cyclone Lane (August 29, 2018)
Updated schedule for limited local access to Wainiha, Haena via Kuhio Highway effective October 15, 2018 (October 3, 2018)
Cultural gathering held to celebrate Waioli, Waipa & Waikoko Bridges (November 7, 2018)
Holiday/Sunday convoy schedule for local access to Wainiha and Haena updated Nov. 21 (November 21, 2018)
Nighttime closure of Kuhio Highway (Route 560) at Waioli Bridge scheduled for December 11, 2018 (December 4, 2018)
Single lane restriction on Kuhio Highway (Route 560) at Hanalei Hill for emergency survey work, December 10-14, 2018 (December 7, 2018)
 
Copyright © 2018 Kūhiō Highway Emergency Repairs Team, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.

Email Marketing Powered by Mailchimp